The Town of Chapel Hill recently provided updates to two parking deck projects downtown: one that is weeks away from beginning and another that is experiencing delays.
Construction on the 125 East Rosemary Street parking deck has been hampered by a recent discovery. The Chapel Hill Town Council received an update during its November 16 meeting that detailed how after demolition of the prior deck, contractors did not find the bedrock foundation expected. Town staff said that foundation, which was expected to help the base of the seven-level facility, was up to ten feet lower in the ground than expected.
To address this, the town council approved $9 million to fill that extra space with micropiles, which are known for providing strong bases deep into the ground despite having smaller diameters. The approved funding, which will be paid for through the town’s fund balance and additional financing later, brings Chapel Hill’s total financial commitment to the construction project to around $48 million.
Town staff said during the town council meeting that construction delays pushes the estimated time of opening for the parking deck from spring 2023 closer to November 2023. The project broke ground in September 2021.
While much attention is directed toward 125 East Rosemary Street, another public deck down the street is preparing for some maintenance work of its own.
Chapel Hill announced the public parking deck at 140 West Franklin Street is preparing for some rolling closures of spaces in order to complete repairs from water leaks. The deck, which also have private parking for the condominium community above businesses occupying ground floor space, will experience closures to 30 parking spaces at a time for the restoration and waterproofing efforts. At the same time, the town will complete resurfacing to the plaza and install additional bollards to prevent vehicles from driving on the plaza level.

An aerial view of 140 West Franklin Street. On the back side of the building is the entrance to a level of public parking off Rosemary Street. (Photo via the Town of Chapel Hill.)
The town’s release said spaces on the public parking level will start to be closed off around mid-December, with contractors expected to hang plastic drapes to prevent some dust or debris from making it onto parked cars in the deck. Chapel Hill also said residents at the 140 West condominium community will see their private space blocked overnight at some point in the construction project — with more information set to be communicated to the residents closer to that date.
The full release from the Town of Chapel Hill on the 140 West Rosemary Street parking deck repairs can be found here. More information about parking accessibility across Chapel Hill can be found on the town’s parking website.
Featured photo via Perkins + Will.
Chapelboro.com does not charge subscription fees, and you can directly support our efforts in local journalism here. Want more of what you see on Chapelboro? Let us bring free local news and community information to you by signing up for our biweekly newsletter.
Related Stories
‹

Spaces in Chapel Hill's Rosemary-Columbia Parking Lot to Close for ConstructionMore than two dozen parking spaces in Chapel Hill will be lost for the foreseeable future ahead of major development on East Rosemary Street. The town government recently alerted the community the lower section of the Rosemary-Columbia Parking Lot will be closed off beginning Monday, February 22. The area will be used to stage and […]

Chapel Hill Approves Agreement for Major East Rosemary Development with 5-3 VoteThe Chapel Hill Town Council took a significant procedural step to the start of major development planned along East Rosemary Street in the coming years. With a 5-3 vote at its Wednesday meeting, the council approved Town Manager Maurice Jones to enter a development agreement with Grubb Properties, who plans to construct a new parking […]

Pair of Projects Set to Close E. Rosemary Street in Chapel Hill for Nearly 2 WeeksA popular downtown street in Chapel Hill will close for around two weeks due to a pair of projects, according to the town government. An update shared Thursday said East Rosemary Street between Columbia Street and Henderson Street will close to through traffic starting on Saturday. The projects are the Orange Water and Sewer Authority […]

'New Era for Downtown': Chapel Hill Opens East Rosemary Street Parking DeckThe parking deck at 125 East Rosemary Street in Chapel Hill is set to open to the public on Monday, August 26 after a brief ribbon-cutting.

East Rosemary Street Reopens to Traffic in Chapel Hill as Parking Deck Construction ProgressesEast Rosemary Street in Chapel Hill reopened on Monday, which is the latest sign of the parking deck's construction progressing.

Town of Chapel Hill Receives Design Updates, Financial Projections for East Rosemary Street DevelopmentA major development project for East Rosemary Street in downtown Chapel Hill continues to progress, as the town council recently heard updates on the latest details for a new parking deck. Town officials hope the 125 East Rosemary Street site, where one parking deck owned by Grubb Properties currently stands, will be where a newer […]

Chapel Hill Mayor: Harnessing Local Passion Part of Town's 2025 PlansChapel Hill Mayor Jess Anderson says plenty comes to mind for town government goals and what her aspirations are for this new calendar year.

Chapel Hill's New Rosemary Street Parking Deck Begins Charging FeesChapel Hill announced the 125 East Rosemary Street deck will begin charging its normal parking rates to users on Monday.

Carrboro Unveils New Crosswalk Art; Chapel Hill Seeks Muralists for Parking Deck PorchWhile the Town of Chapel Hill is preparing for a new public art project, the Town of Carrboro just put the finishing touches another. Carrboro shared new artwork painted at the bend of Roberson Street near the Libba Cotten Bikeway, meant to accentuate the crosswalk and lighten up the area near The ArtsCenter. The piece […]

Chapel Hill Details Delays on New Parking Facility; Water Leak Repairs Needed for Another DeckThe Town of Chapel Hill recently provided updates to two parking deck projects downtown: one that is weeks away from beginning and another that is experiencing delays. Construction on the 125 East Rosemary Street parking deck has been hampered by a recent discovery. The Chapel Hill Town Council received an update during its November 16 […]
›