The Town of Chapel Hill recently provided updates to two parking deck projects downtown: one that is weeks away from beginning and another that is experiencing delays.
Construction on the 125 East Rosemary Street parking deck has been hampered by a recent discovery. The Chapel Hill Town Council received an update during its November 16 meeting that detailed how after demolition of the prior deck, contractors did not find the bedrock foundation expected. Town staff said that foundation, which was expected to help the base of the seven-level facility, was up to ten feet lower in the ground than expected.
To address this, the town council approved $9 million to fill that extra space with micropiles, which are known for providing strong bases deep into the ground despite having smaller diameters. The approved funding, which will be paid for through the town’s fund balance and additional financing later, brings Chapel Hill’s total financial commitment to the construction project to around $48 million.
Town staff said during the town council meeting that construction delays pushes the estimated time of opening for the parking deck from spring 2023 closer to November 2023. The project broke ground in September 2021.
While much attention is directed toward 125 East Rosemary Street, another public deck down the street is preparing for some maintenance work of its own.
Chapel Hill announced the public parking deck at 140 West Franklin Street is preparing for some rolling closures of spaces in order to complete repairs from water leaks. The deck, which also have private parking for the condominium community above businesses occupying ground floor space, will experience closures to 30 parking spaces at a time for the restoration and waterproofing efforts. At the same time, the town will complete resurfacing to the plaza and install additional bollards to prevent vehicles from driving on the plaza level.

An aerial view of 140 West Franklin Street. On the back side of the building is the entrance to a level of public parking off Rosemary Street. (Photo via the Town of Chapel Hill.)
The town’s release said spaces on the public parking level will start to be closed off around mid-December, with contractors expected to hang plastic drapes to prevent some dust or debris from making it onto parked cars in the deck. Chapel Hill also said residents at the 140 West condominium community will see their private space blocked overnight at some point in the construction project — with more information set to be communicated to the residents closer to that date.
The full release from the Town of Chapel Hill on the 140 West Rosemary Street parking deck repairs can be found here. More information about parking accessibility across Chapel Hill can be found on the town’s parking website.
Featured photo via Perkins + Will.
Chapelboro.com does not charge subscription fees, and you can directly support our efforts in local journalism here. Want more of what you see on Chapelboro? Let us bring free local news and community information to you by signing up for our biweekly newsletter.
Related Stories
‹

Chapel Hill Approves Agreement for Major East Rosemary Development with 5-3 VoteThe Chapel Hill Town Council took a significant procedural step to the start of major development planned along East Rosemary Street in the coming years. With a 5-3 vote at its Wednesday meeting, the council approved Town Manager Maurice Jones to enter a development agreement with Grubb Properties, who plans to construct a new parking […]

'New Era for Downtown': Chapel Hill Opens East Rosemary Street Parking DeckThe parking deck at 125 East Rosemary Street in Chapel Hill is set to open to the public on Monday, August 26 after a brief ribbon-cutting.

East Rosemary Parking Deck Faces Increased Costs, Demolition Set for JulyAt the Town of Chapel Hill’s latest town council meeting, developers gave an updated timeline for the East Rosemary parking deck and detailed why the development will cost the town more than $10 million in unforeseen construction costs.

Spaces in Chapel Hill's Rosemary-Columbia Parking Lot to Close for ConstructionMore than two dozen parking spaces in Chapel Hill will be lost for the foreseeable future ahead of major development on East Rosemary Street. The town government recently alerted the community the lower section of the Rosemary-Columbia Parking Lot will be closed off beginning Monday, February 22. The area will be used to stage and […]

Town of Chapel Hill Still 'Negotiating' On Rosemary Street Parking Deck as Summer Break BeginsThe Chapel Hill Town Council had a full agenda for its last scheduled meeting before a summer break last Wednesday. One item not discussed, however, was a formal economic development agreement for a proposed parking deck on East Rosemary Street. The town and Grubb Properties, the developers applying for the project, are still in discussions […]

E. Rosemary Street Redevelopment Negotiations ContinueThe Chapel Hill Town Council met virtually for a work session Monday night to discuss the East Rosemary Street redevelopment. This multi-million-dollar undertaking is being fronted by the Town of Chapel Hill and real-estate developer Grubb Properties. Despite having to meet virtually, negotiations surrounding the 3.2 acres of redevelopment along East Rosemary Street continue to […]

Chapel Hill Town Council Discusses Petitions, Parking Project, and Advisory BoardsThe Chapel Hill Town Council met to hear public petitions, increase funding for a parking deck project, and address advisory board rules.
![]()
Chapel Hill: The Latest on Legion Pond, Budget Discussions and Downtown ProjectsChapel Hill Mayor Pam Hemminger speaks with 97.9 The Hill on Thursday, May 18 about the previous night's council work session.

Chapel Hill Approves New Apartment Building on E. Rosemary StreetTwo projects aim to provide more housing on East Rosemary Street – with one recently being approved by the Chapel Hill Town Council.

Chapel Hill Details Delays on New Parking Facility; Water Leak Repairs Needed for Another DeckThe Town of Chapel Hill recently provided updates to two parking deck projects downtown: one that is weeks away from beginning and another that is experiencing delays. Construction on the 125 East Rosemary Street parking deck has been hampered by a recent discovery. The Chapel Hill Town Council received an update during its November 16 […]
›