The latest sign of the East Rosemary Street parking deck’s progress came to fruition on Monday: the road in front of the construction area is open for the first time in nearly eight months.
The Town of Chapel Hill shared social media posts on Monday celebrating the reopening of a stretch of East Rosemary’s 100 block that had been closed since August 2023. The closure was in part to create construction staging for a crane to install several pieces of the new, seven-story parking deck — but the crane’s work wrapped up recently and the machine was removed earlier in April. While both nearby parking sites remained accessible during the closure, it allows all forms of traffic to run from North Columbia Street to Henderson Street unfettered once again.
“Thank you for your patience with this road closure,” the town government said in its weekly newsletter and a video about Monday’s reopening. “It allowed the contractor to more quickly and safely move the massive concrete deck pieces into place.”
The town-owned East Rosemary parking deck has suffered several hurdles in its construction since breaking ground in September 2021. The structure at 125 East Rosemary Street needed to be dug lower into the ground than expected, causing several delays from the initial fall 2022 opening date Chapel Hill had shared. The delays and soaring construction costs also led the local government’s spending on the project to cross $50 million — increasing from the initial $30 million estimates for the deck in 2021. Town officials, however, say the deck is on track to be completed in the summer and once open, it will provide around 1,100 parking spots to Chapel Hill community members and visitors.
When speaking with 97.9 The Hill in late February, Chapel Hill Town Manager Chris Blue said the town government’s goal is to have the new East Rosemary parking deck up and running by the summer.
“If you go by and take a look [at the deck],” he said, “you’ll see it is really starting to look like something we’re all excited about parking in really soon. By early summer, we’re hoping to have things open and for business.
“Taking the long view,” Blue continued, “having this deck available to our downtown businesses, visitors to downtown, folks coming to football games and campus-related events, this is going to be a game-changer and we’re very, very excited about it.”
Chapelboro.com does not charge subscription fees, and you can directly support our efforts in local journalism here. Want more of what you see on Chapelboro? Let us bring free local news and community information to you by signing up for our newsletter.
Related Stories
‹

Date Set for Demolition of East Rosemary Street Parking DeckAfter a few delays, the Town of Chapel Hill announced that the demolition of the Rosemary Street Parking Deck will begin Saturday, July 31. The demolition of the parking deck is the first step towards the East Rosemary Street Redevelopment project, which includes the demolition of the existing “CVS” parking deck to construct a new, […]

East Rosemary Street Developers Share Plans for New Chapel Hill ApartmentsThe proposed Link Apartments would add approximately 140 new units at the northeastern corner of East Rosemary and North Columbia streets.

East Rosemary Street Development to Begin Demolition in JuneThe East Rosemary Street development is just a few weeks away from initial construction – with demolition expected to begin in June.

Spaces in Chapel Hill's Rosemary-Columbia Parking Lot to Close for ConstructionMore than two dozen parking spaces in Chapel Hill will be lost for the foreseeable future ahead of major development on East Rosemary Street. The town government recently alerted the community the lower section of the Rosemary-Columbia Parking Lot will be closed off beginning Monday, February 22. The area will be used to stage and […]

Town of Chapel Hill Receives Design Updates, Financial Projections for East Rosemary Street DevelopmentA major development project for East Rosemary Street in downtown Chapel Hill continues to progress, as the town council recently heard updates on the latest details for a new parking deck. Town officials hope the 125 East Rosemary Street site, where one parking deck owned by Grubb Properties currently stands, will be where a newer […]

Chapel Hill Mayor: Harnessing Local Passion Part of Town's 2025 PlansChapel Hill Mayor Jess Anderson says plenty comes to mind for town government goals and what her aspirations are for this new calendar year.

Pair of Projects Set to Close E. Rosemary Street in Chapel Hill for Nearly 2 WeeksA popular downtown street in Chapel Hill will close for around two weeks due to a pair of projects, according to the town government. An update shared Thursday said East Rosemary Street between Columbia Street and Henderson Street will close to through traffic starting on Saturday. The projects are the Orange Water and Sewer Authority […]

Chapel Hill's New Rosemary Street Parking Deck Begins Charging FeesChapel Hill announced the 125 East Rosemary Street deck will begin charging its normal parking rates to users on Monday.

'New Era for Downtown': Chapel Hill Opens East Rosemary Street Parking DeckThe parking deck at 125 East Rosemary Street in Chapel Hill is set to open to the public on Monday, August 26 after a brief ribbon-cutting.

East Rosemary Street Reopens to Traffic in Chapel Hill as Parking Deck Construction ProgressesEast Rosemary Street in Chapel Hill reopened on Monday, which is the latest sign of the parking deck's construction progressing.
›